Project Implementation Progress
Information on the implementation of project activities, results achieved and events held.
Overall implementation progress
Key milestones
-
PIU establishment and project start-up
Completed 01.09.2025 — 31.12.2025
Establishment of the unit, approval of the procurement plan and reporting arrangements.
100% -
Design and environmental assessment
Completed 01.10.2025 — 31.03.2026
Preparation of design documentation and the environmental and social impact assessment.
100% -
Procurement under Components 1 and 2
In progress 01.01.2026 — 31.12.2026
Conduct of tenders and award of contracts for works and equipment.
60% -
Construction and installation works
In progress 01.05.2026 — 30.06.2028
Modernization of the pumping stations and reconstruction of the maintenance base.
15% -
Commissioning and training programmes
Planned 01.01.2028 — 30.06.2029
Commissioning of the facilities and delivery of training programmes for beneficiaries.
0%