Project Implementation Progress

Information on the implementation of project activities, results achieved and events held.

Overall implementation progress

55%

Key milestones

  • PIU establishment and project start-up

    Completed  01.09.2025 — 31.12.2025

    Establishment of the unit, approval of the procurement plan and reporting arrangements.

    100%
  • Design and environmental assessment

    Completed  01.10.2025 — 31.03.2026

    Preparation of design documentation and the environmental and social impact assessment.

    100%
  • Procurement under Components 1 and 2

    In progress  01.01.2026 — 31.12.2026

    Conduct of tenders and award of contracts for works and equipment.

    60%
  • Construction and installation works

    In progress  01.05.2026 — 30.06.2028

    Modernization of the pumping stations and reconstruction of the maintenance base.

    15%
  • Commissioning and training programmes

    Planned  01.01.2028 — 30.06.2029

    Commissioning of the facilities and delivery of training programmes for beneficiaries.

    0%